The Challenge

Following storm-related damage at the 342 MW Solar PV Plant, Datasee.AI was engaged to assess the site's condition and identify modules requiring further investigation. Spanning approximately 950 acres with an installed capacity of 342 MWp, the site presented the challenge of systematically assessing potential damage across a large-scale solar installation.

The task went beyond identifying anomalies. Understanding the condition of affected modules and connecting observations to their precise locations was essential to support further investigation and prioritise follow-up actions.

Our Solution

Datasee.AI conducted a drone-based thermal inspection of the solar plant in July 2026. The inspection identified potential module defects and abnormal thermal patterns, with findings categorised and linked to location-specific references across the site.

By combining aerial inspection data with module-level identification, Datasee.AI provided a structured view of the reported conditions, helping the site team locate observations and plan further assessments.

342 MWp

Installed solar capacity inspected

~950 acres

Plant area

6 days

Inspection period

39,945*

Number of Defected Modules

Impact

From Damage Assessment to Risk Prevention

The inspection provided location-specific information about reported module conditions, including panel failures, broken glass, hotspots, dirt, and diode-related issues. These findings supported a more targeted approach to investigating potential damage and planning follow-up assessments.

However, the incident also raises a broader question: Could better site planning and construction monitoring help reduce certain risks before a solar plant becomes operational?

What If Risk Assessment Began Earlier?

Had Datasee.AI's wider geospatial and engineering solutions been incorporated during the development of the 342 MW Solar PV Plant, they could have helped identify and address certain site-related vulnerabilities before construction was completed.

Topographic Survey and Hydrology Analysis: Understanding terrain, slopes, and drainage pathways could have informed site planning and helped identify areas requiring closer assessment for runoff and water accumulation.

Grading and Cut-and-Fill Assessment: Terrain modelling could have supported more suitable grading and earthwork decisions based on site conditions.

Construction Progress Monitoring (CPM): Monitoring construction against planned layouts and design requirements could have helped identify deviations requiring corrective action.

Construction Quality Monitoring (CQM): Documenting visible construction issues and verifying work against applicable quality requirements could have supported better construction oversight.

These measures cannot guarantee protection against severe storms. However, when applied appropriately, they can help project teams identify and address certain preventable site-planning, drainage, grading, and construction-quality risks that may influence infrastructure performance during adverse weather.

The Datasee.AI Advantage

At Datasee.AI, our role extends beyond identifying issues after they occur. We bring together geospatial intelligence, engineering assessment, construction monitoring, and drone-based inspection to help renewable energy developers make informed decisions throughout the project lifecycle.